  • Ahmedabad-Dholera Expressway Progress: As of June 30, 2024, 71 km of the 109 km expressway is completed, with the entire project expected to finish in the 2024-25 financial year. The project costs Rs. 4,372 crores, with Rs. 3,920 crores already spent.

  • Expected Commute Time: The Ahmedabad-Dholera Expressway will enable travel between Ahmedabad and Dholera in approximately 40 to 45 minutes once operational.

  • Delhi-Mumbai Expressway Progress: Out of the 1,386 km Delhi-Mumbai Expressway, 1,070 km is completed, with the entire project set to finish in the 2025-26 financial year.

  • Delhi-Vadodara Section: 804 km of the Delhi-Vadodara section is completed, with only 41 km remaining.

  • Vadodara-Mumbai Section: 214 km of the 450 km Vadodara-Mumbai section is completed. The total expenditure on the Delhi-Mumbai Expressway so far is Rs. 56,990 crores out of the estimated Rs. 1 lakh crores.