The Ahmedabad-Dholera expressway, a key project initiated by Prime Minister Narendra Modi, is likely to be completed before the 2024 Lok Sabha elections.
-
Originally scheduled for January 2024, the project faced delays due to heavy rainfall in 2023, but construction has picked up pace recently.
-
The first phase, from Sanathal to Sindhrej, is expected to be completed by March 2024, with about 70% of the work done in some areas.
-
The expressway, divided into four packages, will have a top speed of 120 km per hour, two toll plazas, and refreshment spots.
-
Once completed, the expressway will significantly reduce travel time, allowing a 45-minute commute to Dholera and reducing the journey to Bhavnagar to 1.45 hours from the current 3 hours.